Scoping, pre-feasibility or bankable: choosing the right study

Feasibility work is done in stages because each stage costs more than the last. Commissioning the wrong level of study either wastes money on detail that is not yet needed, or leaves a decision without enough evidence behind it.

The usual sequence

Terms vary between industries, but most projects move through three levels of study before a final investment decision.

  • Scoping or concept study. Tests whether there is a project worth pursuing. Uses benchmarks and high-level estimates, often within plus or minus 30 to 50 per cent. It answers: should we spend money investigating this?
  • Pre-feasibility study. Compares the main options for site, size, technology and route to market, and selects one. Cost estimates are typically within plus or minus 25 to 30 per cent. It answers: which version of the project should we develop?
  • Feasibility or bankable study. Develops the chosen option in enough detail to support investment and financing. Estimates are normally within plus or minus 10 to 15 per cent, with key contracts and permits well advanced. It answers: should we build it, and can it be financed?

Which one do you need now?

Start from the decision that has to be made next and who will rely on the study.

  • If you are deciding whether to acquire land, a licence or an option, a scoping study is usually enough.
  • If you are choosing between sites, capacities or technologies, or approaching equity investors, a pre-feasibility study is the right tool.
  • If you are seeking debt finance, a government concession or a board decision to commit capital, you need a full feasibility or bankable study.

Related studies

Several other types of study sit alongside this sequence.

  • Techno-economic feasibility reports combine technical design and financial appraisal, and are common for industrial and process plants.
  • Detailed project reports are often required by public authorities and development lenders, with a prescribed format.
  • Value-for-money and PPP studies compare public procurement with private finance for infrastructure.
  • Independent reviews test a study prepared by someone else, usually for a lender or investor.

Avoiding common waste

The most expensive mistake is starting a bankable study while key choices are still open. Every change of site, technology or capacity means repeating engineering, market and financial work. The second most common is skipping pre-feasibility altogether and discovering, late, that a different option would have been better.

Our feasibility studies page sets out what each level of study covers, and we can advise on the right starting point for your project.

Discuss a transaction or project

Tell us what you need answered and when. We reply with a scope, a timetable and a fixed or capped fee.

Request a proposal