Stalled projects: getting the cost to complete right

A project that has stopped halfway through construction is often available at a discount. Whether that discount is real depends on one number: what it will cost, and how long it will take, to finish. Technical due diligence on a stalled project is mostly about getting that number right.

Why stalled projects are different

On a new project, cost risk sits in the estimate. On a stalled project, it also sits in the work already done. Structures may have deteriorated while exposed, equipment may be out of warranty or obsolete, permits may have lapsed, and the records needed to prove what was built may be incomplete. A buyer or lender who prices only the remaining scope, using the original contract rates, will usually be wrong.

What the review covers

  • Condition survey. Inspection of completed works, with testing where needed, to establish what can be relied on, what needs repair and what must be replaced.
  • As-built verification. Comparison of what exists on site with drawings, specifications and quality records, including any structural or geotechnical investigation needed to confirm foundations.
  • Remaining scope. A list of work still to be done, priced at current market rates rather than the original contract.
  • Remediation and preservation. The cost of repairing deterioration and protecting the works until construction restarts.
  • Equipment. Status of delivered and stored equipment, warranties, and the cost of re-commissioning or replacement.
  • Permits and approvals. Which approvals are still valid, which must be renewed, and whether rules have changed since they were granted.
  • Contracts and claims. Position with the original contractor and subcontractors, including unpaid amounts, liens and potential claims that could follow the asset.
  • Programme. A realistic schedule to completion, including mobilisation, procurement and commissioning.

Turning findings into a number

The output is a cost-to-complete estimate with a stated accuracy and a contingency that reflects the uncertainty in each category. Remediation of unknown conditions normally carries a higher contingency than remaining new work. The report should present a base case and a downside case, so that a lender can size its facility and a buyer can set a price that leaves room for surprises.

Monitoring after funding

Once funding is in place, the same technical adviser is often appointed to monitor progress, certify drawdowns against work completed, and report on cost and schedule each month. This gives lenders early warning if the project starts to slip again.

Our technical due diligence and lender's technical adviser services cover both the initial review and ongoing monitoring.

Discuss a transaction or project

Tell us what you need answered and when. We reply with a scope, a timetable and a fixed or capped fee.

Request a proposal